Update from Kevin Varness/Ryan Bartelheimer
3/19/2014
- Negotiations soon to begin regarding aquisition of two parcels by the County.
- Additional environmental field work is scheduled for the Spring.
- 30% design is planned for June 2014.
- 60% design and permit submittals are planned for August 2014.
- Construction cost estimate has been preliminarily revised downward from $5.4 million to $4.7 million.
- See project update memo from Ryan Bartelheimer (click here).
|