Update from Rob Wilson
1/12/2017
From Steve Schmitz (KPFF):
Completed - SEPA Determination of Non-Significance issued by GHC.
- HPA and JARPA Permits are under review with WDFW & Army Corp.
- 60 Percent Plans, Specs, and Engineers Estimate have been completed & reviewed by GHC.
Upcoming - Incorporation of GHC and permitting agency comments to Plans and Specifications.
- Preparation of final bid documents.
- Bid date in Spring of this year.
- Construction beginning in July 2017.
Renderings
From Scott Boettcher (Chehalis River Basin Flood Authority):
A "Lower Basin Information Sharing Session" was held 12-06-2016 at the Department of Ecology. Presentations from the sharing session can be found here.
|