The project is nearly complete with landscaping, fencing, streetlights the only remaining items to be installed. A ribbon cutting ceremony is scheduled for October 7th at 4 PM to be held at Scott Avenue just west of the roundabout. The public is welcome to attend.
|
Road paving is complete! The roundabout is now in full operation with temporary striping and signage. Sidewalks, streetlights, and landscaping will be finished in the next few weeks.
|
Curbs are complete!
All curbs have been poured! East Scott Avenue is closed to eastbound traffic until September 1st. Paving is next, followed by sidewalks, lighting and landscaping. The interior curbs and roundabout apron were completed last week. The exterior curbs were poured today and yesterday. Paving is scheduled for the week of August 24th. The contractor will pave during the evening on Monday, August 24th and Tuesday, August 25th, and pave during the day... |
7/29/2015
-
Curbs are being poured!
(East Scott Avenue to be closed to eastbound traffic for a few weeks)
673
Concrete Curb Work
Concrete curbs poured today! Interior roundabout and splitter island concrete work will be completed this week. Exterior curbs will be poured in a couple weeks after the interior curbs have adequate cure time without traffic. Paving is tentatively scheduled for the last week in August and will be done in the evening. The underground utility work is mostly complete now and should be finished by the end of next week. East Scott Avenue... |
The City of Woodland awarded a construction contract to Tapani, Inc. as the low bidder for the Lewis River Road/Scott Avenue Intersection Project. A Notice to Proceed with construction work was issued by the City on June 1, 2015.
Construction is scheduled for completion in October 2015. The following is a general breakdown of the work: Removals and roadway demolition - June Construct storm drainage, water and sewer improvements - July Construct curbs, sidewalks, driveways, and roundabout... |
Tuesday, June 17th - 6-8pm
City Council Chambers (in new police station) - 200 East Scott Avenue, Woodland, WA 98674 The City of Woodland is hosting an open house about improving the intersection at Lewis River Rd (SR 503) and Scott Avenue. No formal presentation is scheduled, so drop by anytime during the 2-hour open house. |
Delete File
Are you sure you want to delete article ?
To: | |
CC: | |
BCC: |
Please Wait...