2013-15 Funding -- $521,000 (09/06/2013).
                                 

Description -- The proposed project will design and construct approximately 900 linear feet of dike along the northwest side of the wastewater treatment plant (WWTP) to protect the WWTP from flood events.  The top of the dike will have an elevation of approximately 365.00 feet, which is approximately 2 feet higher than the water level reached in the 2007 flood event. 

Flood Hazard Reduction Benefits -- The WWTP Dike will reduce the risk of flooding at the Town of Pe Ell's WWTP by creating a barrier to flood waters that is 2 feet higher than the level that water reached in the 2007 flood event.  The dike will be constructed in 2014 and will be ready to protect the WWTP in the winter of 2014-15.

Project Status -- Completed.

Schedule/Milestones: 
  • DONE -- July 2014 through mid September 2014 -- Task 3: Construct Dike -- ($465,900).
  • DONE -- June/July 2014 -- Select construction contractor (BC Balmelli Trucking).
  • DONE -- November 2013 through February 2014 -- Task 2: Complete Environmental Review and Obtain Permits -- ($2,500 -- SEPA, Shoreline Permit, Critical Area Permit, Fill and Grade Permit).
  • DONE -- September 2013 through December 2013 -- Task 1: Complete Final Engineering Design -- ($52,600 -- Plans, Specifications and Cost Estimate).
  • DONE -- September 2013 -- Finalize inter-local funding agreement with OFM.  Click here for scope of work.