Update from Kris Koski
4/20/2016
Schedule updates are as follows:
- Apr-May 2016 -- Aerial Survey, Bathymetric Survey, & Hydraulic Analysis.
- May-Jul 2016 -- Alignment Analysis & Concept Design.
- Jul-Nov 2016 -- Utility Survey, Geotechnical Exploration, Biological Evaluation, & 60% Plans.
- Nov 2016-Mar 2017 -- CLOMR Submittal & FEMA Review.
Updated contact information.
|