WA Department of Fish and Wildlife - Lower Satsop Relic Channel

  << Back

Update from Michelle Cramer     1/14/2015

·       To date, the following has occurred:

o  Completed extensive 2D hydraulic modeling.

o  Developed and analyzed a suite of alternatives.

o  Held two stakeholder meetings.

o  Met individually with key stakeholders.

o  Drafted conceptual designs.

 

·       Wetlands delineation, fish survey and cultural resources study will be completed by the end of February 2015. 

·       Another round of stakeholder meetings to share the preferred alternatives will be completed by June 2015. 

·       A time extension (past July 2015) is being requested to include complete 60 percent design plans, basis of design report and preparation of permitting documents due to an approximately six month delayed start to the project.