(3/13/2013) Update from Tim Elsea
4/12/2013
- Phase I Construction (Ditch Clearing 4,200 linear feet outside wetland areas) was completed in February 2013.
- Phase II design work is proceeding. Will need Fill & Grade permit and Washington Parks right of Entry Permit.
- DAHP Excavation permit for Phase II will be submitted this week (up to 60-day review/approval).
- Phase II construction will start prior to July 1, 2013 but this project will require a time extension for the OFM grant.
- See 03/13/2013 update report -- click here.
|