Lewis County - Adna Levee Project

  << Back

(3/13/2013) Update from Tim Elsea     4/12/2013

  • Phase I Construction (Ditch Clearing 4,200 linear feet outside wetland areas) was completed in February 2013.
  • Phase II design work is proceeding.  Will need Fill & Grade permit and Washington Parks right of Entry Permit.
  • DAHP Excavation permit for Phase II will be submitted this week (up to 60-day review/approval).
  • Phase II construction will start prior to July 1, 2013 but this project will require a time extension for the OFM grant.
  • See 03/13/2013 update report -- click here.