Lewis County - Airport Levee Project

  << Back

(3/13/2013) Update from Tim Elsea     4/14/2013

Due to preliminary design assumptions made prior to grant submittal, the original construction timeline is not realistic (complete by June 30, 2013).  Environmental permitting issues and planned Phase IB work fall within the Corps jurisdiction where permit approval is typically very lengthy.  To achieve the desired outcome of base widening to accommodate a future height addition (33-ft top width required), this project will span two summer construction seasons (Phase IA in 2013 and Phase IB in 2014).  Construction will start prior to July 1, 2013 but this project will require a time extension for the OFM grant.