Project Update
11/19/2013
- Construction began July 22, 2013.
- Approximately 80% of work is complete with 36,000 out of 41,000 CY of fill material having been placed.
- Project has experienced several unworkable days due to rain showers and wet sub-grade following rain days.
- Current and anticipated weather requires a construction shutdown until conditions improve for common borrow placement.
- See recent project update letter from Tim Elsea to the Flood Authority -- Click here.
|