Lewis County - Airport Levee Project

  << Back

Project Update     11/19/2013

  • Construction began July 22, 2013.
  • Approximately 80% of work is complete with 36,000 out of 41,000 CY of fill material having been placed.
  • Project has experienced several unworkable days due to rain showers and wet sub-grade following rain days.
  • Current and anticipated weather requires a construction shutdown until conditions improve for common borrow placement.
  • See recent project update letter from Tim Elsea to the Flood Authority -- Click here.