Project Update
6/18/2014
- Construction began July 22, 2013.
- To date, approximately 80% of work is complete.
- The majority of the project is nearly complete with36,000 CY of fill material placed (41,000 CY originally planned for Phase 1A).
- Levee construction will likely resume by July 2014 whenconditions are dry and warm.
- There are 25 working days remaining for the completionof Phase IA construction.
|