Lewis County - Airport Levee Project

  << Back

Project Update     6/18/2014

  • Construction began July 22, 2013.
  • To date, approximately 80% of work is complete.
  • The majority of the project is nearly complete with36,000 CY of fill material placed (41,000 CY originally planned for Phase 1A).
  • Levee construction will likely resume by July 2014 whenconditions are dry and warm.
  • There are 25 working days remaining for the completionof Phase IA construction.