Cosmopolis - Mill Creek Dam Improvement Project

  << Back

Update from Darrin Raines     1/13/2015

·       Project schedule has been updated.

·       The budget is 67% complete.

·       For construction in 2016 the fish window for in‑waterwork is assumed to be June 1 to September 30.

·       New schedule is:

o  November 2015 to October 2016 -- Pending funding.  Task Order 5 "Bidding and Construction.

o  March 2015 to October 2015 -- Pending funding.  Task Order 4 "Final Design and Permitting."

o  January 2014 to March 2015 -- Engineer's Report and Long-Lead Permit Application.