Update from Darrin Raines 1/13/2015 · Project schedule has been updated. · The budget is 67% complete. · For construction in 2016 the fish window for in‑waterwork is assumed to be June 1 to September 30. · New schedule is: o November 2015 to October 2016 -- Pending funding. Task Order 5 "Bidding and Construction. o March 2015 to October 2015 -- Pending funding. Task Order 4 "Final Design and Permitting." o January 2014 to March 2015 -- Engineer's Report and Long-Lead Permit Application.
|