zoom+R
Today is
[Portal ID #1838]

Lewis River Road/Scott Avenue Intersection Project

  << Back

Curbs are complete!  (Paving is next)  8/14/2015

Curbs are complete!

All curbs have been poured! East Scott Avenue is closed to eastbound traffic until September 1st.

Paving is next, followed by sidewalks, lighting and landscaping.

The interior curbs and roundabout apron were completed last week.  The exterior curbs were poured today and yesterday.  Paving is scheduled for the week of August 24th.  The contractor will pave during the evening on Monday, August 24th and Tuesday, August 25th, and pave during the day on Wednesday, August 26th and Thursday, August 27th.  After paving is complete, sidewalks, lighting, and landscaping will be constructed.

<< Back