Bucoda - Main Street Regrade Project

  << Back

Update from Mayor Carr     12/17/2015

The following schedule updates are based on the best information available right now:

  1. Project Planning Meeting with Stakeholders: January, 2016.
  2. Presentation and Discussions of Options and Costs: February, 2016.
  3. Client Selection of Option Used to Prepare 30% Plans: February 2016.
  4. Design Memorandum of the Selected Option: March, 2016.
  5. Preliminary Survey and Boundary Work: March, 2016.
  6. Begin Property Owner Negotiations: March, 2016.
  7. Write Legal Descriptions for Acquisitions: April, 2016.
  8. 30% Plans submittal: April, 2016.
  9. Complete Property Acquisitions: May 6, 2016.
  10. Prepare Earthwork Quantities: June, 2016.
  11. Begin Environmental Permitting Reviews: July, 2016.
  12. Hydraulic Modeling: July, 2016.
  13. Prepare Geotechnical Report: July, 2016.
  14. 60% Plans Submittal, Draft Project Manual, Updated Cost Estimate: August, 2016.
  15. Structural Engineering, September, 2016.
  16. 90% Plans Submittal, November, 2016.
  17. Bid Set Plans, Bid Call, Engineer’s Est: December, 2016.
  18. Open Bids: January, 2017.
  19. Begin Construction, February, 2017.
  20. Complete Construction: June 30, 2017.