Update from Mayor Carr
12/17/2015
The following schedule updates are based on the best information available right now:
- Project Planning Meeting with Stakeholders: January, 2016.
- Presentation and Discussions of Options and Costs: February, 2016.
- Client Selection of Option Used to Prepare 30% Plans: February 2016.
- Design Memorandum of the Selected Option: March, 2016.
- Preliminary Survey and Boundary Work: March, 2016.
- Begin Property Owner Negotiations: March, 2016.
- Write Legal Descriptions for Acquisitions: April, 2016.
- 30% Plans submittal: April, 2016.
- Complete Property Acquisitions: May 6, 2016.
- Prepare Earthwork Quantities: June, 2016.
- Begin Environmental Permitting Reviews: July, 2016.
- Hydraulic Modeling: July, 2016.
- Prepare Geotechnical Report: July, 2016.
- 60% Plans Submittal, Draft Project Manual, Updated Cost Estimate: August, 2016.
- Structural Engineering, September, 2016.
- 90% Plans Submittal, November, 2016.
- Bid Set Plans, Bid Call, Engineer’s Est: December, 2016.
- Open Bids: January, 2017.
- Begin Construction, February, 2017.
- Complete Construction: June 30, 2017.
|