Centralia - China Creek Project

  << Back

Update from Kahle Jennings     3/12/2016

  • We received comments from Lewis County during SEPA review.
    • A second project redesign was prepared and reviewed with Lewis County. They had additional comments so additional survey work was completed and a final project design should be completed by the end of the week. Changes in the final design are minor.
    • SEPA DNS (Determination of Nonsignificance) including conditions to address Lewis County concerns has been issued.
  • JARPA has been submitted.
  • AquaTera has been contracted with for cultural resources review. That is underway.
  • We will begin preparing bid specifications so that when the JARPA process is complete we will be ready to go out to bid.
  • Project is on-track.