Centralia - China Creek Project

  << Back

Update from Kahle Jennings     4/21/2016

Done to Date:

  • RCO Contract signed 11-3-15.
  • Phase 1 SEPA issued 11-23-15; reissued 12-7-15.
  • SEPA Comments received 12-22-15 resulting in project redesign.
  • Ecology Shorelands Program Management Team visited project site 3-16-16.
  • Project poster prepared by consulting engineer sent to Scott Boettcher for possible posting on EZview 4-4-16.
  • JARPA was submitted 4-4-16.
  • Cultural Resources Assessment completed 4-11-16.
  • Cultural Resources Assessment submitted to RCO 4-11-16.
  • Received Invoice from Lewis County for Planning Review, Flood Permit and Grading Permit 4-11-16.
  • Project signs were printed and installed 4-13-16 (Photos provided).
  • Cultural Resources Assessment forwarded to USACE 4-19-16 5-19-2016.

Pending:

  • We are currently waiting for responses to JARPA permit application.