Centralia - China Creek Project

  << Back

Update from Kahle Jennings     9/14/2016

  • US Army Corps of Engineers notified me on August 25th that they have completed Section 7 ESA review.  We are still reviewing Section 106 National Historic Preservation Act and Dredged Materials. They requested and I sent them a copy of the cultural resources assessment. We had anticipated this and already completed it.
  • Soil testing of the construction site will occur this week.
  • Biologists will be in the field at China Creek on Friday of this week (Sept 16) and Thursday and Friday (Sept. 22 and 23) of next week to work on the habitat and biology baseline surveys.  We have a sampling plan that has been approved by WDFW and they have been notified. 
  • Construction for Phase I will now be Summer 2017.