Bucoda - Main Street Regrade Project

Summary of the project
Last Updated: October 19, 2016

 

Click HERE To Return To Main Flood Authority Website  
 
Click HERE to Return To Bucoda Flood Relief Projects
(www.ezview.wa.gov/bucodafloodrelief))
 
Click HERE To See Project Financials
 
2015-17 Funding -- $3,100,000 (9/25/2015, click here)
 
Project Financials -- See separate project financials website here.
 
Description -- The proposed project involves elevating approximately 1,500 feet of Main Street a height of 4 to 6 feet (and 8-10 feet at the culverts themselves).  Additionally, 150+ feet of opening would need to be installed near the intersection of Main Street and 11th Street to provide an overflow path for Skookumchuck River flood waters. The opening will likely consist of multiple box culverts or a bridge.
 
Flood Hazard Reduction Benefits -- Overbank flooding on the Skookumchuck River results in the closure of Main Street near the intersection with 11th Street in the Town of Bucoda.  Approximately 50 residences (25% of the Town) located south of 11th Street are isolated from emergency services during high flow events.  In January 2009, the homes and citizens were cut off from the rest of town for two days.
 
Project Status -- "On-Hold" (see 9-13-2016 update here).

Schedule/Milestones -- Current high-level schedule is as follows: 
  • TBD (formerly Summer 2016) -- Final Design Complete.
  • TBD (formerly October 2016) -- Property Acquisition Complete.
  • TBD (formerly June 2017) -- Construction Complete.

Current detailed schedule sequence is as follows: 

  1. DONE -- Project Planning Meeting with Stakeholders: January, 2016.
  2. DONE -- Presentation and Discussions of Options and Costs: February, 2016.
  3. DONE -- Client Selection of Option Used to Prepare 30% Plans: February 2016.
  4. DONE -- Design Memorandum of the Selected Option: March, 2016.
  5. DONE -- Preliminary Survey and Boundary Work: March, 2016.
  6. DONE -- Begin Property Owner Negotiations: March, 2016.
  7. DONE -- Write Legal Descriptions for Acquisitions: April, 2016.
  8. DONE -- Community Meeting: May 19, 2016.
  9. DONE -- 30% Plans submittal: July 1, 2016
  10. Complete Property Acquisitions: TBD
  11. Prepare Earthwork Quantities: TBD
  12. Begin Environmental Permitting Reviews: TBD
  13. Hydraulic Modeling: TBD
  14. Prepare Geotechnical Report: TBD
  15. 60% Plans Submittal, Draft Project Manual, Updated Cost Estimate: TBD
  16. Structural Engineering: TBD
  17. 90% Plans Submittal: TBD
  18. Bid Set Plans, Bid Call, Engineer’s Est: TBD.
  19. Open Bids: TBD.
  20. Begin Construction: TBD.
  21. Complete Construction: TBD.