Update from Alan Vanell (6/19/2013)     6/20/2013

I reviewed the EZ view link regarding our project.

We received the Project Manual for the Bucoda Levee Improvement Project for the Town of Bucoda prepared by Jerome W. Morrissette & Associates Inc., P. S. dated June 4th, 2013.  In the manual is the finalization of the Bid Documents as described on the EZview link.  We have the drawings (24” x 36”) showing: 
A. Site Plan
B. Existing Condition & Demolition Plan
C. Erosion Control Plan
D. Erosion Control Notes & Details
E. Layout Plan
F. Levee Sections & Details
G. Storm & Surface Restoration Details

Our Total YTD spending:                32,759.91             78% of Budget
Budgeted Amount:                         42,000.00
                                                _________________________
Remaining:                                          9,240.09              22% Remaining   (will not be spent by July 1, 2013)

I talked with Mayor Carr. He said within the past week he received communication from O.F.M. stating the deadline of July 1, 2013 will be extended to July 1, 2014.