Update from Bob Amrine
1/13/2014
- Still assessing a few sites.
- There will likely be 8 to 11 new critter/equipment pad sites and 1 new evacuation route.
- Two of the original 5 critter pads will be added to for farm equipment.
- Surveying and designing the structures should begin in February 2014.
- Permit applications will be submitted mid to late April 2014.
- Contracting and construction are planned for July 2014.
|