Montesano - Revetment to Protect Montesano Rd., WWTP and Mary's River Lumber Project

  << Back

Update from Steve Schmitz     2/18/2014

  • City of Montesano was granted approval by Flood Authority to proceed with expediting the construction at the WWTP.
  • Stellar J and City of Montesano met for an on-site kick-off of the WWTP project on Thursday 2/13/2014.
  • Stellar J plans on beginning construction at the WWTP on Monday 2/24/2014.
  • Stellar J plans on beginning mobilization this week, with construction trailer and equipment beginning to arrive on Wednesday 2/19/2014.
  • Submittals for various items have been provided by Stellar J and are currently being reviewed by Parametrix.
  • Construction surveying will begin tomorrow Tuesday 2/17/2014 at the WWTP.