Update from Steve Schmitz
3/19/2014
- To date we have installed approximately 440 linear feet of the 1482 feet proposed for the WWTP.
- Soil conditions have varied widely from those initially shown in the geotechnical report which initially slowed down installation.
- Currently the Contractor is averaging between 75 and 100 feet of sheet piles installed per day for the WWTP.
- Installation of the sheet piles should be completed within 2 weeks, with work at the entrance gate beginning shortly thereafter.Milling and delivery of the steel sheet piling for the Mary’s River Mill site is still on schedule for June.
- See project schedule here.
|