zoom+R
Today is
[Portal ID #1751]

Montesano - Revetment to Protect Montesano Rd., WWTP and Mary's River Lumber Project

  << Back

Update from Steve Schmitz     3/19/2014

  • To date we have installed approximately 440 linear feet of the 1482 feet proposed for the WWTP.
  • Soil conditions have varied widely from those initially shown in the geotechnical report which initially slowed down installation.
  • Currently the Contractor is averaging between 75 and 100 feet of sheet piles installed per day for the WWTP.
  • Installation of the sheet piles should be completed within 2 weeks, with work at the entrance gate beginning shortly thereafter.Milling and delivery of the steel sheet piling for the Mary’s River Mill site is still on schedule for June.
  • See project schedule here.

<< Back