Montesano - Revetment to Protect Montesano Rd., WWTP and Mary's River Lumber Project

  << Back

Project Update     6/18/2014

  • This project has two primary construction phases.  Phase I is construction of flood protection levee around the waste water treatment plant.  Phase II is construction of sheet pile flood protection levee at the Mary’s River Lumber site.
  • Phase I (WWTP) is complete and finished as of 6-02-2014.
  • Phase II (Mary’s River Lumber site) began construction June 16, 2014 and should be complete by end of August 2014.
  • Initial projections are that Phase I and Phase II will be completed approximately $400,000 under budget.  This number will be clearer in July 2014.
  • Click here for photos showing construction and completion (Phase I, WWTP) of the projects.