Update from Steve Willie 7/20/2016 Project is at 30% design. 30% design cost estimate projects full construction cost in excess of $8M (formerly $3M). Project will be reviewed and discussed at 7/21/2016 Flood Authority meeting in light of this new cost projection. High level schedule items have been changed to TBD pending direction from 7/21/2016 Flood Authority Meeting. See Scope Change Memo --> Click here. See 30% Design (design drawings) --> Click here. See 30% Design (cost estimate) --> Click here.
|