Elma - WWTP Outfall Stabilization Project

  << Back

Update from Michael Marshall     5/18/2016

  Recent Work Completed:

  • prepared and submittied JARPA application including Critical Areas report, Biological Evaluation, and Mitigation Plan.
  • published the SEPA DNS determination and received comments.

Upcoming Work:

  • responding to additional information request from Corps.
  • working to receive HPA from WDFW.
  • finishing contract specifications.
  • complying with 05-05 artifacts including contacting all associated tribes and submitting an EZ1 form to DAHP.

Once we have all required permits in hand, we plan to go to bid.  Note: Original bid date will be delayed due additional information request noted above.

See updated PRISM project milestone progress report here.

 

 