Update from David Fleckenstein     12/17/2015

  1. Skillings Connolly, Inc. out of Lacey, WA was selected to design and oversee construction of the pump house.
  2. We are currently working to complete the contract for the agreed upon scope of work.
  3. Our next step is to have a geo-technical company complete the analysis of soils required for the design. Once we have a design in hand we can provide you with a copy to post the concept design on line.
  4. We have also linked up the Corps of Engineers with Skillings Connolly earlier in the week and will check to see if Kristen Hafer is in the loop.