Chehalis - Chehalis-Centralia Airport Pump Project

  << Back

Update from David Fleckenstein     7/20/2016

Schedule:

Adjustments have been made to the overall timelione due to delays in finalizing geo-technical questions and concerns, as well WDFW requirements for fish exclusion/dewatering and concluding work prior to the end of the DFW fish window (SEP 30th).

Skillings Connolly is preparing final structural design for the pump house.

See revised timeline here.

Funding/Cost:

Airport and Flood Authority Projects Committee will review recent cost information presented by Skillings Connolly in light of above described regulatory requirements, additional geo-technical work, and revised structural designs and considerations.  