Napavine - Kirkland Road Flooding Project

  << Back

Update from Steve Ashley     1/19/2016

Project updates are as follows:

  • The City of Napavine authorized Gray & Osborne, Inc. to begin work on the project on November 10, 2015.
  • A site visit was conducted on December 15, 2015.
  • A hydraulic model was developed using the Ecology Western Washington Hydraulic Model.
  • A drainage report identifying the basin, projected flows, capacity of the existing system and improvements will be prepared.
  • A basemap and preliminary plans of the identified improvements will be prepared.