Napavine - Kirkland Road Flooding Project

  << Back

Update from Scott Boettcher     4/8/2017

1.  Following have occured in recent weeks regarding the Napavine Kirkland Road Project:

  • 12-19-2016 -- INITIAL Report and Findings -- Click here.
  • 1-31-2017 -- Meeting with County Commissioners Fund and Jackson, City of Napavine, Flood Authority and interested citizens (Breen and Smell).
  • 1-31-2017 -- Comments from Breen and Smell -- Click here (Breen) and here (Smell).
  • 2-08-2017 -- Interest from additional citizen -- Click here (Swanson).
  • 2-21-2017 -- Response to Comments by Gray and Osborne -- Click here.

2.  Following upcoming activities are planned:

  • 4-08-2017 -- Request quote to prepare hydraulic analysis -- Click here.

3.  Budget and expenditures as of 4-08-2017 are:

  • Budget = $40,000
  • Expenditures = $18,488.71
  • Remaining = $21,511.29
  • See more -- Click here.