			·       This project has been discontinued and unspent monies shifted to the City of Aberdeen’s proposed Northside Levee project per Flood Authority decision (9/16/2014 meeting).·       See 9/16/2014 staff memo here. | 
		| 
			
			Project design and engineering is at about 60%. | 
		| 
			
				
 				
              
                3/19/2014
				 - 
				Update Pending 
				 
                
                
			    403
             Update for March 20, 2014 Flood Authority meeting pending. | 
		| 
			
			January 2014 -- 2013-15 inter-local funding agreement with OFM approved. | 
		| 
			
				
 				
              
                11/20/2013
				 - 
				Project Update 
				 
                
                
			    367
             FINAL design is presently 50% complete.Funding request for 2013-15 State Capital Budget funds ($270,000,construction) is pending. | 
		| 
			
			Project schedule has slipped some.Present schedule calls for:End-October 2013 -- FINAL design will be 50% complete and ready for public and agency review.09/12/2013 -- FINAL design is presently at 30%.09/06/2013 -- FINAL preliminary engineering and costing. | 
		| 
			
			The schedule for this project has been received and posted to Library.  Click here to directly access the schedule. | 
		| 
			
			The City is working with the selected consultant (KPFF Consulting Engineers) to put together a contractual agreement. | 
		| 
			
			The city has selected a single consultant for both the Burger King and Wishkah North projects.  We are presently scoping and scheduling with the consultant. |